1. What Is a 220kV Cable GIS Termination?

A 220kV Cable GIS Termination connects a high-voltage underground cable to Gas Insulated Switchgear (GIS). It provides a safe and reliable link between the XLPE power cable and the GIS equipment.

오늘, many power utilities use GIS substations because they need less space than traditional air-insulated substations. 게다가, GIS equipment offers reliable operation and requires less outdoor installation space.

하지만, connecting a 220kV XLPE cable to GIS equipment requires a special cable termination. This accessory must control the electric field, provide strong insulation, and maintain a reliable connection during long-term operation.

A 220kV Cable GIS Termination normally works with 127/220kV or other project-specific cable systems. Engineers must check the rated voltage and insulation level before selecting the product.

Unlike an outdoor cable termination, a GIS termination connects directly to a GIS bushing inside a sealed switchgear compartment. 그러므로, its design must match the GIS interface and the cable structure.

66kV GIS 터미널

2. Main Components of a 220kV GIS Cable Termination

A typical 220kV GIS cable termination contains several important parts. Each part has a clear function in the electrical and mechanical system.

2.1 절연체

The insulating body provides electrical insulation between the high-voltage conductor and the grounded GIS enclosure.

Manufacturers commonly use silicone rubber or epoxy-based materials for this component. These materials offer good insulation strength and stable performance.

게다가, the insulating body must withstand normal operating voltage, lightning impulses, and switching impulses. Its design also needs to meet the requirements of the complete cable system.

2.2 Stress Control Cone

The stress control cone plays a key role in every high-voltage cable termination.

At the end of the cable insulation screen, the electric field can become very strong. If the termination does not control this stress, partial discharge may occur. 시간이 지남에 따라, this problem can damage the insulation.

그러므로, a 220kV Cable GIS Termination uses a stress control cone or an integrated stress control structure. This design helps spread the electric field more evenly and improves insulation reliability.

2.3 도체 커넥터

The conductor connector links the cable conductor to the GIS contact system.

케이블 디자인에 따라, the conductor may use copper or aluminum. The connector must provide good electrical contact and enough mechanical strength.

뿐만 아니라, engineers must select the correct connector size according to the conductor cross-section and diameter.

2.4 GIS Plug-in Interface

The GIS plug-in interface connects the cable termination to the GIS bushing.

This component requires accurate dimensions and a suitable contact design. Even a small difference in the interface dimensions may cause installation problems.

이러한 이유로, customers should provide the GIS manufacturer’s drawings and interface details before ordering a 220kV GIS cable termination.

2.5 Sealing and Grounding Parts

The sealing system protects the insulation area from moisture and external contamination. It also helps maintain the required sealing performance at the GIS connection.

그 동안에, the grounding parts connect the cable metallic screen or sheath to the substation grounding system.

The grounding arrangement depends on the cable bonding design. 그러므로, engineers should confirm it during the project design stage.

110kV GIS 종료

3. Key Features of a 220kV Cable GIS Termination

A reliable 220kV Cable GIS Termination must offer stable electrical performance and strong mechanical design.

Its main features include:

  • High insulation strength: It supports safe operation in 220kV power systems.
  • Good electric field control: The stress control structure reduces local electrical stress.
  • 컴팩트한 디자인: It fits inside GIS equipment and helps save installation space.
  • Reliable sealing: The sealing structure helps prevent moisture from entering the connection area.
  • Low partial discharge: Good insulation design reduces the risk of internal electrical defects.
  • Strong mechanical performance: The termination supports the mechanical loads that may occur during installation and operation.
  • 긴 서비스 수명: Quality materials and proper design help ensure stable performance over many years.

게다가, manufacturers can design different termination sizes to match cable conductor areas, insulation thicknesses, and sheath structures.

4. 220kV GIS Termination for XLPE Power Cables

Most modern 220kV underground transmission projects use XLPE insulated power cables.

A typical 220kV XLPE cable includes the following layers:

  1. 구리 또는 알루미늄 도체
  2. 도체 반도체 스크린
  3. XLPE 단열재
  4. 절연 반도체 스크린
  5. 금속 스크린, usually copper wires or tape
  6. Water-blocking layer, if required
  7. Aluminum or lead metallic sheath, 디자인에 따라
  8. Outer protective jacket

The 220kV Cable GIS Termination must match the cable structure. 예를 들어, a copper conductor cable may need a different connector from an aluminum conductor cable.

비슷하게, different metallic screen and sheath designs may require different grounding arrangements.

생산 전, the customer should provide the following cable information:

  • 정격전압
  • 도체 재료
  • 도체 단면적
  • 도체 직경
  • XLPE 단열재 두께
  • Insulation screen diameter
  • Metallic screen structure
  • 케이블 외경

With these details, the manufacturer can check the cable dimensions and select a suitable termination design.

GIS 종료

5. Installation Process of a 220kV Cable GIS Termination

Correct installation plays an important role in the performance of a 220kV GIS cable termination.

Because this product works in an extra-high-voltage system, qualified technicians should follow the manufacturer’s installation manual and approved project procedures.

The general installation process includes the following steps.

단계 1: 케이블 준비

첫 번째, technicians should check the cable length and installation position. They must also fix the cable securely before starting the work.

다음, they remove the outer jacket, metallic sheath, and other cable layers according to the installation dimensions.

이 과정에서, technicians must protect the XLPE insulation from scratches and other damage.

단계 2: Prepare the Insulation Surface

After removing the required cable layers, technicians prepare the XLPE insulation surface.

The surface must remain clean, smooth, and free from dust or contamination. Any deep scratch or uneven area may affect the electric field distribution.

그러므로, technicians should use the correct tools and follow the manufacturer’s surface preparation instructions.

단계 3: Install the Stress Control Component

다음, technicians install the stress cone or integrated stress control unit.

They must place this component in the correct position because it controls the electric field around the insulation screen.

Incorrect positioning may increase electrical stress and reduce the service life of the termination.

단계 4: 지휘자를 연결하십시오

After preparing the cable conductor, technicians connect it to the GIS contact connector.

They must clean the contact surfaces and follow the specified tightening torque or crimping procedure.

A good conductor connection reduces contact resistance and helps prevent overheating during operation.

단계 5: Connect the GIS Interface

그 다음에, technicians connect the termination to the GIS bushing.

They should carefully check the alignment, insertion depth, contact position, and sealing components.

게다가, the installation team must follow the GIS manufacturer’s requirements for the plug-in connection.

단계 6: Complete the Final Inspection

마지막으로, the installation team checks the complete assembly.

They should inspect the mechanical connection, 접지 시스템, sealing parts, and cable support structure.

프로젝트 요구 사항에 따라, the team may also carry out electrical tests before energizing the system.

Indoor terminaation

6. IEC Standards for 220kV Cable GIS Terminations

International standards help manufacturers and power utilities maintain product quality and electrical safety.

Several IEC standards are relevant to 220kV cable systems.

IEC 62067

IEC 62067 covers power cables with extruded insulation and their accessories for rated voltages above 150kV up to 500kV. 그러므로, it is particularly important for 220kV XLPE cable systems.

IEC 62271-203

This standard covers gas-insulated metal-enclosed switchgear for rated voltages above 52kV. It provides important requirements for GIS equipment.

IEC 60270

IEC 60270 describes high-voltage test methods for partial discharge measurement. This test helps identify possible insulation defects.

IEC 60840

IEC 60840 covers extruded insulation power cables and their accessories for rated voltages above 30kV up to 150kV. Although it does not cover 220kV systems, it is relevant to lower-voltage cable projects.

For a 220kV Cable GIS Termination, engineers should pay special attention to IEC 62067 and the relevant GIS equipment requirements.

The project specification should also define the required type tests, routine tests, and acceptance tests.

Cable GIS Termination

7. Electrical Tests for 220kV GIS Cable Terminations

Electrical tests help confirm the insulation quality and operating performance of a 220kV cable termination.

The main tests may include the following:

Partial Discharge Test

Partial discharge testing helps detect small electrical discharges inside the insulation system.

A low partial discharge level indicates good insulation quality. 그러므로, this test plays an important role in high-voltage cable accessory qualification.

Power Frequency Voltage Test

This test checks whether the insulation system can withstand the required AC test voltage for a specified period.

It helps confirm the dielectric strength of the termination.

Lightning Impulse Test

Lightning impulse testing checks the ability of the insulation system to withstand short-duration high-voltage surges.

This test is important because lightning can create high transient voltages in power transmission networks.

Switching Impulse Test

For extra-high-voltage systems, switching impulse performance also plays an important role in insulation coordination.

The test checks the termination’s ability to withstand switching overvoltages under the specified test conditions.

Thermal Cycling Test

Thermal cycling tests help evaluate the performance of cable accessories under repeated heating and cooling.

During normal operation, the conductor temperature changes with the electrical load. 그러므로, the termination must maintain stable electrical and mechanical performance during these temperature changes.

The exact test sequence and acceptance limits depend on the applicable IEC standard and project requirements.

GIS 터미널

8. Applications of 220kV Cable GIS Terminations

220kV GIS cable terminations support many types of high-voltage power projects.

220kV GIS Substations

Power utilities use GIS terminations to connect underground cables to GIS switchgear in high-voltage substations.

Urban Underground Transmission

Large cities often use underground power cables to reduce the need for overhead transmission lines. GIS substations also help save valuable land.

Power Plants

Power plants use 220kV cable systems to connect transformers, 개폐 장치, and transmission networks.

산업시설

Large industrial plants need a stable electricity supply. A 220kV cable GIS termination helps connect their high-voltage cable circuits to GIS equipment.

재생 가능 에너지 프로젝트

Wind farms and large solar power plants may use high-voltage underground cables to connect their substations to the main power grid.

In all these applications, the correct termination design helps maintain safe and reliable power transmission.

9. How to Choose a 220kV Cable GIS Termination

Selecting the correct 220kV Cable GIS Termination requires attention to both cable and GIS equipment specifications.

주문하기 전에, customers should confirm the following information:

매개변수Required Information
정격전압127/220kV or project-specific rating
도체 재료구리 또는 알루미늄
도체 크기Cross-sectional area in mm²
케이블 절연XLPE
단열재 두께According to cable design
금속 스크린구리선, tape, or other structure
케이블 외경Actual cable dimensions
GIS 제조사Brand and equipment model
GIS 인터페이스Interface type and drawing
Installation positionIndoor GIS installation
적용규격IEC 62067 및 프로젝트 사양

Among these parameters, GIS interface compatibility is especially important.

Different GIS manufacturers may use different bushing designs and connection dimensions. 그러므로, customers should provide the GIS interface drawings before ordering.

뿐만 아니라, the cable manufacturer and termination supplier should check all cable dimensions together. This step helps prevent installation problems and reduces project risks.

GIS 종료

10. 220kV Cable GIS Termination Manufacturer – DOS Group

DOS Group is a professional manufacturer and supplier of high-voltage cable accessories and power transmission products in China.

We provide cable termination and jointing solutions for high-voltage and extra-high-voltage power systems. Our product range covers 66kV, 110케이 V, 132케이 V, 145케이 V, 220케이 V, 245케이 V, and other project-specific voltage levels.

Our main products include:

  • 220kV Cable GIS Terminations
  • 220kV Outdoor Cable Terminations
  • High Voltage XLPE Cable Joints
  • GIS Plug-in Cable Terminations
  • Dry-Type Cable Terminations
  • Underground Power Cable Accessories

DOS Group can develop suitable solutions according to cable specifications, GIS interface drawings, 및 프로젝트 요구 사항.

We work with power utilities, EPC 계약자, electrical engineering companies, and international project suppliers.

If you are looking for a reliable 220kV Cable GIS Termination manufacturer or supplier, contact DOS Group. Our team can provide technical specifications, product drawings, installation manuals, and competitive quotations for your project.